Case Study

Case Study: A $30 Million Construction Bridge for a Part-Complete Branded Villa Scheme in Dubai

Twenty-five branded villas in Meydan District 11, land owned outright, build part-way through, and a bank market that would not fund it. How we structured and placed the requirement with private credit, and what made it fundable.

Anonymised at the sponsor's request. The project name, sponsor and lender are withheld. Figures are rounded. This is a real transaction we structured and placed; the terms described are indicative of the facility secured and are not a template or an offer.

The deal at a glance

ElementDetail
Asset25 branded luxury villas, 254,000 sq ft built-up area
LocationDistrict 11, Meydan, Dubai
StagePart-complete; approximately 26 months of construction remaining
LandOwned outright and unencumbered, valued at around $105m
Facility$30m senior secured construction-to-sale bridge, 27 months
Cost to completeAround $77.7m, giving a loan-to-cost of 38.6%
GDVAround $221m
Pre-sales5 units contracted before completion, roughly $80m of non-cancellable value
SecurityFirst legal charge over the plot, assignment over units, charge over escrow receivables

The situation

The sponsor had done the difficult part. The land was bought and paid for outright, planning was in place, the brand was secured, and construction was under way on a 25-villa scheme a short drive from the centre of Dubai. What they did not want to do was fund the remaining build entirely from their own balance sheet, because that capital had better uses and the timeline was stretching.

The requirement was not a purchase facility or a refinance. It was completion capital: money to carry the scheme through roughly 26 months of construction to handover, repaid from sales rather than from a refinance at the end. In the UK, that is a familiar conversation. In Dubai, it is not, because the market does not have a bridging industry in the way London does.

Why the banks would not do it

The sponsor had already tested the conventional route and the answer was predictable.

None of that made the deal bad. It made it wrong for a bank's credit policy, which is a different thing entirely.

How we sourced the funding

The work was less about finding a lender and more about presenting the asset so that the right lender could see what it actually was. Five things did the heavy lifting.

1. We reframed the land as the credit story

Most construction requests arrive as a request for risk capital. This one had roughly $105m of unencumbered land sitting in the capital stack, which meant the lender was not really taking construction risk at all. Against a $30m facility, the land alone represented a loan-to-value of under 29%. Once that was framed as the first-loss buffer it is, the conversation changed from "should we fund a build" to "how do we document against prime Dubai land".

2. We built the cost to complete from the ground up

The number that kills construction facilities is an unrealistic cost to complete. We worked from the remaining budget of roughly $77.7m, with contingency, and showed the facility as 38.6% of it. A lender can underwrite 39% loan-to-cost. It cannot underwrite a sponsor who has not counted properly.

3. We used pre-sales as the exit, not as decoration

Five units were contracted before completion, representing around $80m of non-cancellable sales value. That is 2.7 times the facility before a single further villa is sold. Presented properly, that is not a marketing statistic, it is the repayment source, and it moves the deal from speculative to bankable.

4. We made the escrow the lender's control mechanism

Dubai's regulated escrow framework is often described as a compliance burden. In this transaction it was the opposite. Buyer instalments flow into a monitored project account on a 70/30 structure, roughly $5.3m a month during construction against contractor draws of about $3m. That surplus is what allows a 50% cash sweep: half of each month's receipts pays down interest and principal automatically, and the facility extinguishes itself by the end of the term rather than relying on a refinance at handover.

5. We structured the security to match the asset

First legal charge over the plot, assignment over the units, and a charge over the escrow receivables. In a market where lenders otherwise rely on a share pledge over the borrowing company, this package gave the lender direct control of the cash rather than indirect control of a company. That is a materially better position, and it is what allowed the pricing to sit where it did.

The facility secured

Indicative terms of the solution placed, summarised for the purposes of this case study:

The structural point worth understanding is the sweep. A facility repaid at maturity depends on the market being kind at exactly the wrong moment. A facility that sweeps half of every month's receipts from a government-monitored escrow account repays itself on a schedule that has nothing to do with sentiment. That is the difference between construction finance that completes and construction finance that ends in a conversation about extension fees.

What the lenders challenged, and how we answered it

ChallengeOur answer
Is the land really worth that?We supported value with acquisition evidence and a lender-accepted valuation rather than the sponsor's own figure.
What if the build overruns?Contingency within the cost to complete, a fixed-price contract with a credible contractor, and monthly monitoring surveyor certification before each draw.
Are the pre-sales real?Contracted, non-cancellable reservations registered within the regulated escrow framework, not letters of intent.
Who controls the cash?The escrow charge and the sweep mechanism, with drawdowns released only against certified works.
What if sales slow?Modelled downside absorption, not the base case, and showed cover from the existing contracted backlog alone.

What this structure teaches other sponsors

  1. Equity already in the deal is your best negotiating tool. A sponsor with paid-for land is not asking a lender to take a punt; they are asking them to lend against a buffer. Say so plainly and prove it.
  2. Pre-sales belong in the credit paper, not the brochure. Contracted revenue is a repayment source. Quantify the cover, per month, not in aggregate.
  3. Cost to complete has to survive interrogation. Every lender has seen a sponsor's optimistic budget. A properly costed one with contingency is worth more than a lower number.
  4. Control beats covenant. A lender who controls the cash flow will price better than one relying on promises. Structure the escrow charge early.
  5. Do not ask a bank to be something it is not. If your deal needs 60% leverage, speed and a construction structure, private credit is the market. Arriving at that conclusion three months earlier saves more money than negotiating the rate.

Where this fits

The same structure appears repeatedly in cross-border work: a part-complete scheme, an owned asset, contracted demand and a sponsor who needs completion capital rather than a sale. If you are funding a development in the UAE, we can look at facilities from AED 70 million through private credit, and if the right answer is a UK-secured facility against British property, that is usually cheaper and we will say so.

Frequently asked questions

Was this a bridging loan or development finance?

Both, in effect. It is a construction-to-sale facility: it funds remaining build costs and repays from sales during the term rather than requiring a refinance at the end. UK readers can think of it as development finance with a bridging exit built in.

Why private credit rather than a bank in Dubai?

The leverage, the speed and the structure. Regional banks generally cap out at 40% to 50% loan to value and take months to reach credit committee. Private credit prices higher and moves faster, which was the right trade for this programme.

Can a UK-based sponsor borrow in the UAE?

Yes, subject to entity structuring, source of funds and AML requirements. Cross-border ownership adds due diligence rather than blocking the transaction.

What is the minimum facility size?

The UAE private credit facility we access starts at AED 70 million. Smaller requirements are better served by a UK-secured facility or by an in-country lender with a lower floor, and we will tell you which applies.

Funding a development abroad?

Send us the appraisal, the cost to complete and the sales position. We will tell you honestly whether it is fundable, and what would need to change if it is not.

Start a Conversation

Related reading

Anonymised case study. Details have been rounded and identifying information removed at the sponsor's request. Terms are indicative of the facility placed and do not constitute an offer of credit. Facilities secured on property outside the UK generally fall outside UK mortgage regulation.